Comprehensive renewal of Prunéřov II - desulphurization

Realization

2012-2014

Description

Realization:

Basic design (initial project) 2008-2009

Detail Design (project realization) 2009-2011

Workshop documentation 2012-2013

Production and delivery of 08 / 2012-05 / 2014

Installation: 10 / 2012-12 / 2014

Place: Prunéřov, area Prunéřov II

Description:

Piping raw gas by 5.7 meters - 800 tons Tanks and absorbers

- 1200 t Technological steel structure

- 1700 t Customer: ANDRITZ Energy & Environment GmbH, Austria

Description:

- Design work from initial design to shop documentation

- The development control plan for production and assembly

- Quality control of production - Supervision of European Welding Engineer (IWE) on site

- Implementation of visual and capillary tests on site

- Production and delivery of steel structures

- Installation of welded and bolted steel structures

- Applications corrosion protection