















Realization
2007
Description
Realization:
Place: Tušimice, Czech Republic
Description:
The erection was divided in three stages with respect to shutdown plan of production blocks and progress of an installation of new boilers.
The erection of the steel structure and installation of the technological equipment was carried out as a part of the project of the flue gas desulphurization plant for the power plant Tušimice II. The scope of performance involved preparation work (erection organisation, welding procedure specifications, inspection and testing plans), erection work and relevant checks including measuring and setting records.