Realization: 04/2011 - 08/2012
Place: Počerady, Czech Republic
Description: The new source is constructed in power Počerady nearby existing coal-fired power plants. Fire resistance soluted as local fire. Reinforced concrete ceilings with drawn reinfor-cement of corrugated sheets.
Detail design of steel structure Engineering steam turbine. Workshop 3D model and workshop drawings of steel constructions Engineering flue gas turbines. Workshop 3D model and workshop drawings of steel constructions Engineering steam turbines. Steel construction exported into the PDMS format, which served to coordinate the General designer steel construction and technology. 3D computer models of coordination especially in solving secondary support structures internal distribution process steam.